Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the impeka domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/klient.dhosting.pl/pekabex/backup/BK-pekabex.com/wp-includes/functions.php on line 6170
Conclusion of a significant contract by a subsidiary of Poznańska Korporacja Budowlana Pekabex S.A. | Pekabex - budownictwo prefabrykowane

Conclusion of a significant contract by a subsidiary of Poznańska Korporacja Budowlana Pekabex S.A.

Conclusion of a significant contract by a subsidiary of Poznańska Korporacja Budowlana Pekabex S.A.

The Management Board of Poznańska Korporacja Budowlana Pekabex S.A. (“the Issuer”) informs that the Issuer’s subsidiary – Pekabex Bet S.A. (“the Company”) has concluded a contract today with Dachland sp. z o.o., the detailed terms and conditions of which are set out below:

Subject of the contract: execution of a prefabricated reinforced concrete structure for the investment “Expansion of the hall of the Fluid Department” of the Reckitt Benckiser Production (Poland) Sp. z o.o. “, located in Nowy Dwór Mazowiecki

Contract value: 2% of the revenues of the Pekabex Group according to the last published annual consolidated financial statements (in full percentages)

Works/delivery start date: 15.11.2021 r.

Works/delivery completion date: 15.05.2022 r.

Warranty period: 60 months Statutory warranty period: 60 months

Performance bond: 5% of the net contract value

Retention bond: 2,5% of the net contract value

Limit of contractual penalties which may be imposed on the contractor/supplier: 10% of the net contract value

The possibility of claiming supplemental compensation: none

Other terms and conditions of the contract deviating from those typical for this contract type: none

The reason for considering the Information as material: The contract value exceeds 5% of the value of the Issuer’s consolidated equity according to the last published annual consolidated financial statements.